Selected installations

PROJECT REPORT • CLOSE-CONTROL COOLING

Seven STULZ CCUs. Fourteen refrigeration circuits.

A controlled replacement programme delivered around live manufacturing, restricted services routes and a critical Christmas shutdown.

Live manufacturing R513A Approx. 700kW
STULZ condenser banks installed within an external manufacturing plant area
External STULZ condenser installation
Equipment7 STULZ CCUs
Refrigeration14 circuits
CapacityApprox. 100kW per unit
ProgrammeOctober to New Year

THE PROJECT

Refrigeration infrastructure prepared while production continued.

UK Cooling and Heating Services supported a multi-phase close-control cooling programme at a live UK manufacturing facility. The featured phase covered seven STULZ units, each with two independent refrigeration circuits and approximately 100kW of cooling capacity.

Much of the insulated pipework and containment had to be installed around operational production areas before the shutdown. That preparation allowed the final connections, testing and commissioning activities to be completed within the restricted Christmas and New Year window.

The site has since become a repeat environment for UKCH, with approximately 15 systems supported across several live-production and shutdown phases.

UKCH SCOPE

Refrigerant-side delivery from route planning to handover support.

The installation was sequenced around manufacturing operations, access limitations and the final shutdown programme.

01

Pipework & containment

Structured insulated refrigerant services routed and supported through congested internal and external plant areas.

02

External condensers

Installation and connection of the associated STULZ condenser equipment and refrigeration services.

03

Pressure testing

Controlled testing of all 14 circuits before evacuation, charging and commissioning activity.

04

Evacuation & charging

Deep evacuation followed by R513A refrigerant charging in accordance with the system requirements.

05

Shutdown coordination

Advance installation work completed while production remained live, ready for final works during the Christmas shutdown.

06

Commissioning support

Technical assistance through system start-up, operating checks and successful project handover.

THE RESULT

A shutdown-ready installation, successfully commissioned.

The advance works reduced the amount of installation activity required during the shutdown itself. All featured circuits progressed through pressure testing, evacuation, R513A charging and commissioning support, enabling the replacement cooling systems to be brought into operation successfully.

Discuss a similar project View precision-cooling capability